Question: Q 4 . ( a ) What are the purposes of doing short - circuit and open - circuit tests for a transformer? ( 5

Q4.(a) What are the purposes of doing short-circuit and open-circuit tests for a transformer?
(5 marks)
(b) A 400kVA,50Hz,11KV220V single-phase transformer has an internal impedance of 5% p.u. The open-circuit test (at rated voltage) of the transformer shows it has a power loss of 3 kW . The short-circuit test (at rated current) of the transformer shows it has a power loss of 6 kW .
When the high voltage side of the transformer is fixed at 11 kV , estimate:
(i) The transformer's internal impedance refers to the lower voltage side;
(5 marks)
(ii) The transformer voltage regulation at a load power factor of 0.8 lagging;
(10 marks)
(iii) The transformer efficiency when it is half-loaded at a power factor of 0.8 lagging.
(5 marks)
Q 4 . ( a ) What are the purposes of doing short

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Electrical Engineering Questions!