Question: Q . 4 Construct a network so as to satisfy the scheduling requirements shown in the table below. table [ [ Activity ,

Q.4 Construct a network so as to satisfy the scheduling requirements shown in the table below.
\table[[Activity,\table[[Preceding],[Activity]],\table[[Duration in days]],Optimistic,\table[[Most],[Probable]],Pessimistic],[10,22,22,,,,],[B,-,20,20,20,,,,],[C,-,4,10,16,,,,],[D,A,2,14,32,,,,],[E,B,C,8,8,20,,,,],[F,B,C,8,14,20,,,,],[G,B,C,4,4,4,,,,],[H,C,2,12,16,,,,],[I,G,H,6,16,38,,,,],[J,D,E,2,8,14,,,,]]
a) Find the time required to complete the whole project and identify the critical activities.
b) What is the probability that the project will be completed within 50 days assuming nomal distribution?
c) What deadline are you 98% sure of meeting?
(20)
 Q.4 Construct a network so as to satisfy the scheduling requirements

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!