Question: Q 5 ( 3 0 Points ) , Section shown belaw belorgs to an Open pit Copper mine. Required amaunt of are: 4 . 4

Q5(30 Points), Section shown belaw belorgs to an Open pit Copper mine.
Required amaunt of are: 4.48**105m3year
Sub-drilling for ore: 2m
lopding density; 120kgm,
Powder Foctor: 0.4kgtan,
Driling Rote (Ore): 21mh
don: 2 tan/m
Net working time ha year: 280 days/hear
Net working time for drilling moch: 2200hryear,50minhr
Net working time for truck and shovel: 12hr? day
Dipper cycle time: 30 sec.
For Truck:
Empty tranel time (t1):244 sec
Spot time at the shovel (t3): 60 sec
Trawel loaded time [tu)380sec
Dump time [ts]: 90sec
According to the data given abowe;
a. Find; Bank weight, Charge amount, Weight of rock broken per drill hole, Number of holes needed, Hole spacing, Holes per year, Total drilling [m] per year and Number of drilling machines needed?
b. Calculate load time for a truck, cycle time for a truck, number of cycle in a day, truck capacity for one day and number of trucks needed (If you have 80 tons truck and truck filled with 4 dipper buckets).
Q 5 ( 3 0 Points ) , Section shown belaw belorgs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!