Question: Q 5 . Considering the information given in Table, at week 2 4 of a project to develop a unique electronic tablet, the project manager
Q Considering the information given in Table, at week of a project to develop a unique electronic tablet, the project manager is worried about her budget since costs have risen to $ Find if there is a cost overage, and if so how much it is Is the schedule ahead or behind? Overall, does the project appear to be in control? Discuss the project state in detail. Marks
tableActivityPredecessor,tableDurationin weekstableBudgetStable