Question: Q 5 ) For the project below, draw the precedence diagrarn and, calculate the normal, least cost, and crash durations. Calculate the cost associated with

Q5) For the project below, draw the precedence diagrarn and, calculate the normal, least cost, and crash durations. Calculate the cost associated with each duration. Indirect (overhead) costs are $120 per day