Question: Q . 5 Set. ( A ) Use the information contained below to compress one time unit per move using the least oost method. Redwee

Q.5Set. (A) Use the information contained below to compress one time unit per move using the least oost method. Redwee the shedule unili you reach the crash point of the network. For cach move identify what activity(s) was erathed, the affusted total cost, and explain your chotce if you hiave to choose between wctivitien that oost the same.
Note: Crash poim of the network is the point in which the duration cannoe be reduced any furtber.
\table[[Activity,Crash Cost,Maximum,,],[II,(Slope),Crash Time,Normal Time Normal Cost,],[A,,0,4,570],[B,$60,2,5,60],[C,50,1,5,90],[D,40,2,4,70],[E,40,1,5,50],[F,50,2,5,40],[G,30,1,4,70],[H,30,1,4,80],[I,,0,3,40]]
Total Direct Normal Costs - $570
Completion Time: 21
Total Cost $570?
 Q.5Set. (A) Use the information contained below to compress one time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!