Question: Q . 6 Consider the following software planning problem. The system consists of 1 1 modules ( M 1 to M 1 1 ) whose

Q.6 Consider the following software planning problem. The system consists of 11 modules (M1 to M11) whose duration (in days). The dependency graph and the duration for each module fin \#days) is shown below
The module implementation has been assigned to three programmers \(-\mathrm{A},\mathrm{B}\), and C as given above, and they will be carried out the tasks assigned in the given sequence.
(a) Using a PERT graph, give the schedule for the above development. Label the nodes with the module names and indicate the earliest possible start/finish time, latest possible start/finish time for each module, and determine the critical path, and hence determine the estimated duration for the project.
(b) What if programmer \( A \) decides to go on a 3-day vacation after completing M8. What impact would this have on the overall schedule with respect to the graph obtained in part (a) of this question? Explain.
Q . 6 Consider the following software planning

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!