Question: Q . 6 Consider the following software planning problem. The system consists of 1 1 modules ( M 1 to M 1 1 ) whose
Q Consider the following software planning problem. The system consists of modules M to M whose duration in days The dependency graph and the duration for each module fin #days is shown below
The module implementation has been assigned to three programmers mathrmAmathrmB and C as given above, and they will be carried out the tasks assigned in the given sequence.
a Using a PERT graph, give the schedule for the above development. Label the nodes with the module names and indicate the earliest possible startfinish time, latest possible startfinish time for each module, and determine the critical path, and hence determine the estimated duration for the project.
b What if programmer A decides to go on a day vacation after completing M What impact would this have on the overall schedule with respect to the graph obtained in part a of this question? Explain.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
