Question: Q . 6 The project in the table below is behind schedule and over budget ( costs in dollars ) : a ) Calculate the

Q.6 The project in the table below is behind schedule and over budget (costs in dollars):
a) Calculate the variances and performance indices at \(100\%\) of the project completion.
b) Calculate the estimated budget at completion (EAC) to finalize this project. Consider cost estimated to completion (ETC) to equal \(\$ 1600\). What is the additional cost to be reported to the management?
Q . 6 The project in the table below is behind

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem we will use Earned Value Management EVM concepts Here are the steps to calcula... View full answer