Q7. Suppose that you have a software project that has these ordered activities [A, B, C, D, G, H] with the associated duration time as indicated in the below table.
By considering the given information. Sketch the Network Diagram by showing the Early Start [ES], Early Finish [EF], Late Start [LS], Late Finish [LF] for each single activity. You assume that the first Activity [A] starts at Day 1. As a result, ES of A=1.