Question: Q. A small bridge project is being evaluated at i=10%. Recommend an alternative based on the capitalized cost for each. Concrete Steel Initial cost $5,000,000

 Q. A small bridge project is being evaluated at i=10%. Recommend

an alternative based on the capitalized cost for each. Concrete Steel Initial

Q. A small bridge project is being evaluated at i=10%. Recommend an alternative based on the capitalized cost for each. Concrete Steel Initial cost $5,000,000 $7,000,000 Annual maintenance cost 45,000 25,000 Major periodic maintenance cost 350,000 450,000 Major maintenance interval 10 years 15 years