Question: Q . NO . 1 . The contractor made the initial node network diagram ( shown below ) but found that activities F , G
QNO The contractor made the initial node network diagram shown below but found that activities F G and I are performed by the same crew, and the contractor has only one crew. Redraw the node network diagram considering the restriction of the contractor? Will the project completion date be delayed? If yes, by how many days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
