Question: Q No.2 Calculate five different overhead rate for cost center AM on the following budgeted data: Labor hours 1400 Total direct labor Rs.3600 Direct material

Q No.2

Calculate five different overhead rate for cost center AM on the following budgeted

data:

Labor hours 1400

Total direct labor Rs.3600

Direct material cost Rs.7500

Machine hour 2850

Units produced 535

Total budgeted factory overhead Rs.12900

(b)

A cost unit has been produced in Cost center AM and following details recorded:

Direct material used Rs.16.5

Direct labor Rs.17.5

Direct labor hours 5.5 hour

Machine hour 8.5 hour

Calculate the cost of the above unit using each of the absorption bases calculated in (a)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!