Question: q1) An SPC chart can only be used with continuous data. True or False q2) Before a DMAIC project is officially concluded, it should contain
q1) An SPC chart can only be used with continuous data.
True or False
q2) Before a DMAIC project is officially concluded, it should contain which 5 of the following?
a.Group of answer choices
b.Follow-up
c.Recommended next steps
d.Description of new team roles
e.Lessons learned
f.Process Owner sign-off
g.Champion sign-off
h. Guidance on how to discipline the team when they fail to sustain the improvements