Question: Q1) Constructing a base-case financial model consists of estimating the future _____ and then computing their ___________. a) cash outflows; net present value b) cash
Q1) Constructing a base-case financial model consists of estimating the future _____ and then computing their ___________.
a) cash outflows; net present value
b) cash flows; future monetary value
c) cash Inflows; future monetary value
d )cash flows; net present value
Q2) The delay in completing tasks _________ results in ____________in project duration.
a) not on critical path; an increase
b) on critical path; an increase
c) on critical path; decrease not
d) on critical path; a decrease
Q3) To complete coupled tasks faster a team should not
a) Increase the numbers of coupled tasks
b) Decouple tasks to avoid iterations.
c) Consider a range of solution instead of a point solution.
d) Perform more iterations quickly.