Question: Q1 : For the jobs shown below determine the sequence and schedule using FIFO, EDD and SPT rules. Calculate for each priority rule : Average

Q1 : For the jobs shown below determine the sequence and schedule using FIFO, EDD and SPT rules.

Calculate for each priority rule :

  1. Average flow time
  2. Makespan
  3. Average tardiness
  4. Average lateness
  5. Number of jobs lateQ1 : For the jobs shown below determine the
Job # Process Time Due Date 1 11 61 2 29 45 3 31 31 4 1 33 5 2 32