Question: Q1. Given the data provided below, (a) draw an AON network, (b) find the critical path, and (c) use the techniques from the lecture (see
Q1. Given the data provided below, (a) draw an AON network, (b) find the critical path, and (c) use the techniques from the lecture (see Probability of on-time completion) to estimate the probability of completing the critical path in 44 days. [This is MM 8e Ch8 P28]
| Time (days) | ||||
| Activity | Predecessor | a | m | b |
| 1 | - | 6 | 10 | 14 |
| 2 | 1 | 0 | 1 | 2 |
| 3 | 1 | 16 | 20 | 30 |
| 4 | 2 | 3 | 5 | 7 |
| 5 | 4 | 2 | 3 | 4 |
| 6 | 3 | 7 | 10 | 13 |
| 7 | 4 | 1 | 2 | 3 |
| 8 | 7 | 0 | 2 | 4 |
| 9 | 3,7 | 2 | 2 | 2 |
| 10 | 9 | 2 | 3 | 4 |
| 11 | 8 | 0 | 1 | 2 |
| 12 | 10,11 | 1 | 2 | 3 |
Q2. Use Excel to do a Monte Carlo simulation for the project given in Q1. Use a triangular distribution to draw the activity times. (a) Show the min, max, and avg project completion time and a histogram of project completion times; (b) estimate the probability of finishing the project in 44 days, and compare with the answer from Q1; (c) now change the optimistic, most likely, and pessimistic times for activity #5 to 15, 25, and 35, respectively. Report the same statistics for this new problem. Why did they change? [This comes from MM 8e Ch8 P30]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
