Q.1. Schneider manufacturing company has following information for March 2019. Budgeted FOH for 10,000 hours $ 30,000
Fantastic news! We've Found the answer you've been seeking!
Question:
Q.1. Schneider manufacturing company has following information for March 2019.
Budgeted FOH for 10,000 hours $ 30,000
Budgeted FOH for 16,000 hours $ 42,000
FOH applied rate for $ 3 per hour
Actual hours worked 15,000 hours
Actual Factory overhead $ 44,000
Required: (10)
1. Determine the fixed portion of the factory overhead application rate.
2. Determine the Variable portion of the factory overhead application rate
3. Determine the Spending and Idle capacity variance
4. Is factory overhead for March is over or under applied, and by how much