Question: Q.1 Study the table below for a project that must be completed in 12 days and answer to the following questions. (Use MS project to

Q.1 Study the table below for a project that must
Q.1 Study the table below for a project that must be completed in 12 days and answer to the following questions. (Use MS project to solve) Activity Predecessor Duration(day) Normal Cost ($) A 3 50 B 1 40 A 3 70 D A 4 20 E B 30 F B 5 30 G CAF 50 H G 60 4 w a. Draw the project network b. Find the ES, EF LS, and LF for all activities. c. Identify all paths, highlight the C.P.? d. Is the project going to be finished within the due date? e. What is the total cost of the project? f. Draw the ES Gantt chart of the project