Question: Q1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Calculate each activity duration using the last digit of
Q1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team.
- Calculate each activity duration using the last digit of your student number. For example, if your number is EMBA 2001524, the last digit is 4 and for activity A the duration is 7+1*4=11.
- Draw a project network diagram (AON), given the following information.
- Complete the forward and backward pass,
- Compute free slack and total slack of each activity
- Identify the critical path.
| Activity | Immediate Predecessor | Duration (Days) |
| A | ------ | 7+1*5 |
| B | ------ | 9+1*5 |
| C | A | 4+2*5 |
| D | B, C | 5+1*5 |
| E | C | 8+1*5 |
| F | D,E | 3+2*5 |
| G | F | 2+1*5 |
| H | F | 1+2*5 |
| I | G | 8+1*5 |
| J | H | 10+1*5 |
Step by Step Solution