Question: Q1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Calculate each activity duration using the last digit of

Q1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team.

  1. Calculate each activity duration using the last digit of your student number. For example, if your number is EMBA 2001524, the last digit is 4 and for activity A the duration is 7+1*4=11.
  2. Draw a project network diagram (AON), given the following information.
  3. Complete the forward and backward pass,
  4. Compute free slack and total slack of each activity
  5. Identify the critical path.

Activity

Immediate Predecessor

Duration (Days)

A

------

7+1*5

B

------

9+1*5

C

A

4+2*5

D

B, C

5+1*5

E

C

8+1*5

F

D,E

3+2*5

G

F

2+1*5

H

F

1+2*5

I

G

8+1*5

J

H

10+1*5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!