Question: Q12. Suppose that the average demand is 170 units per week with a standard deviation of 5 units. The lead time is constant at 4

Q12. Suppose that the average demand is 170 units per week with a standard deviation of 5 units. The lead time is constant at 4 weeks. Determine the reorder point if management wants a 95 percent (cycle-service level (Z=1.65