Question: Q1(a) A certain project involves eight (8) activities identified by the code letters A to H. The table below identifies the sequence in which the

Q1(a) A certain project involves eight (8)

Q1(a) A certain project involves eight (8) activities identified by the code letters A to H. The table below identifies the sequence in which the activities must be undertaken. Construct a network for the project. (30 marks) Activity Code Letter of Any Immediately Preceding Activity or Activities A B. B D E A . F A, C, D G A, C, D H F, G