Question: Q1:Labor Utilization(16 points, 4 parts, 4 pointsfor each part) Consider a process consisting of three resources in a worker-paced line and a wage rate of
Q1:Labor Utilization(16 points, 4 parts, 4 pointsfor each part)
Consider a process consisting of three resources in a worker-paced line and a wage rate of $10 per hour. Assume that there is unlimited demand for the product, and the processing time given for each resource is the time it takes for a single worker to process a unit. When multiple workers work on a single resource, you can assume that the capacity of that resource is given by capacity with a single worker multiplied by the number of workers.

- what is the process flow rate
- what is the cycle time
- How long does it take the process to produce 100 units starting with an empty system?
- What is the direct labor content?
- What is the average labor utilization? (For idle time calculation with multiple workers in each resource, refer to Exhibit 4.2)
- What is the cost of direct labor?
\begin{tabular}{ccc} \hline Resource & Processing time (minutes) & Number of Workers \\ \hline 1 & 10 & 2 \\ 2 & 6 & 1 \\ 3 & 16 & 3 \\ \hline \end{tabular}