Question: Q2: . After estimating a projects NPV, the analyst is advised that the fixed capital outlay will be revised upward by $100,000. The fixed capital
Q2: . After estimating a projects NPV, the analyst is advised that the fixed capital outlay will be revised upward by $100,000. The fixed capital outlay is depreciated straight-line over an eight-year life. The tax rate is 40% and the required rate of return is 10%. No changes in cash operating revenues, cash operating expenses, or salvage value are expected. What is the effect on the project NPV?
A. $100,000 decrease. B. $73,325 decrease. C. $59,988 decrease.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts