Question: Q2.18 A part require three processing steps on two machines in the sequence A-B-A. The demand for this part is 10,000 units per year. The

Q2.18 A part require three processing steps on

Q2.18 A part require three processing steps on two machines in the sequence A-B-A. The demand for this part is 10,000 units per year. The company operate six days per week, eight hour per day. Given the following performance data, find the number of each machine needed to meet the demand. Operation 1 2 3 Machine A B A Standard Time 5min 3min 3min Efficiency 108% 95% 90% Reliability 98% 95% 95% Defects 3% 5% 5%