Question: Q25 QUESTION 25 2 points Peter is running a project with an initial total budget estimate of 2 000 000 rands. His initial assessment of
QUESTION 25 2 points Peter is running a project with an initial total budget estimate of 2 000 000 rands. His initial assessment of cost and schedule performance analysis, reveals that he should have spent R500 000 to date based on his initial plans and a thousand man/days of schedule activities. In reality, on the ground, Peter has spent R600 000 to date and completed 1100 man/days of schedule activities. This should have costed R450 000 based on his initial baseline plan He also estimated that 1500 000 is required to finish the remaining work Calculate Peter's SV measured in man.days. (Please do not leave space/s benveen your digits when writing your answer e.g. is answer is 6000 DO NOT write 6 000 Also leave out the units Le 6000 NOT R6000)