Question: Q.3 (4 Marks) Builder Bug Company allocates overhead at $9 per direct labor hour. Job A45 required 4 boxes of direct materials at a cost
Q.3 (4 Marks) Builder Bug Company allocates overhead at $9 per direct labor hour. Job A45 required 4 boxes of direct materials at a cost of $30 per box and took employees 20 hours to complete. Employees earn $15 per hour. Instructions Compute the total cost of Job A45