Question: Q3. As a contractor you have recently won a construction project. From the past experience, the project manager provided you an estimation of the following


Q3. As a contractor you have recently won a construction project. From the past experience, the project manager provided you an estimation of the following activities: (a) Compute the expected time for each of the listed activities. (4 marks) (b) Draw a precedence diagram (i.e. activity-on-node diagram) for the above project. Determine the earliest start time (ES), latest start time (LS), earliest finish time (EF), latest finish time (LF) and the float (F) for each of the listed activities as shown in the following table. c) Identify the critical path and minimum time to complete the project. ( 2 marks) d) What is the probability of completing the path in less than 78 months