Question: . Q3. Consider the following single machine problem. Job 1 2 3 4 150 6 Process time 8 3 4 6 5 7 Weights 6
Q3. Consider the following single machine problem. Job 1 2 3 4 150 6 Process time 8 3 4 6 5 7 Weights 6 3 1 4 8 5 Due date 6 10 11 12 13 14 (a) Find the optimum sequence that minimize the total weighted completion time. Then compute average weighted tardiness, average weighted completion time, and maximum tardiness. (b) Find the optimum sequence that minimize the maximum lateness. Then compute average weighted tardiness, maximum lateness, and total number of tardy jobs. (c) Find the optimum sequence that minimize the total number of tardy jobs. Then compute average weighted tardiness, total number of tardy jobs, and maximum tardiness.