Question: Q3. Derive a time standard using work sampling. (25 pt)begin{tabular}{|l|l|l|}hline Information & Source of Data & Data for One Day hline begin{tabular}{l} Total time expended
Q3. Derive a time standard using work sampling. (25 pt)\begin{tabular}{|l|l|l|}\hline Information & Source of Data & Data for One Day \\\hline \begin{tabular}{l} Total time expended by operator \\(working time and ldle time)\end{tabular} & Time cards & 480 min \\\hline Number of parts produced & Inspection department & 360 pieces \\\hline Working time in per cent & Work sampling & \(90\%\)\\\hline Idle time in per cent & Work sampling & \(10\%\)\\\hline Average performance index & Work sampling & \(110\%\)\\\hline Total allownaces & Company time -study manual & \(10\%\)\\\hline \end{tabular}