Question: Q3 Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and

Q3 Using the information in Table 1, assuming

Q3 Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: (25 marks) a) Plot the project network. (10marks) b) Determine the critical path of the project. (3 marks) c) Calculate the planned duration of the project in weeks. (3 marks) d) Identify any non-critical tasks and the float (free slack) on each. (4 marks) e) Describe briefly how you transform a WBS into a Network Diagram