Question: Q3(35%) A utility plans to construct a 10 MW gas turbine to meet its peak demand. The plant is to be financed through a loan
Q3(35%) A utility plans to construct a 10 MW gas turbine to meet its peak demand. The plant is to be financed through a loan which costs $70,000 per year for 20 years. The plant is expected to produce 1,000 MWh per year, save S 120,000 per year, and is expected to last 20 years The fuel for the plant costs S20 per MWh and expected to escalate 2% per year. The O&M cost is negligible. The discount rate for the utility is 6%. i) Determine the net present value of this plant. ii) Determine the levelized cost of electricity from this plant
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
