Question: Q4. (20 points) Compare the following alternatives using the Incremental Rate of Return Method (AROR). Given: MARR-8% Alter DOT Construction Life (yrs) cost A B
Q4. (20 points) Compare the following alternatives using the Incremental Rate of Return Method (AROR). Given: MARR-8% Alter DOT Construction Life (yrs) cost A B $250,000 $550.000 Annual Benefits $100,000 S120,000 5 10