Question: Q4) For the project given in the Table 5 answer following questions. (15 marks) Draw the project network diagram. What is the total time required
Q4) For the project given in the Table 5 answer following questions. (15 marks)
- Draw the project network diagram.
- What is the total time required to complete the project if no delays occur?
- When do the individual activities need to start and finish?
- What are the critical bottleneck activities?
- For other activities, how much delay can be tolerated?
Table 5
| Activity | Predecessor | Duration (weeks) |
| A | 5 | |
| B | 4 | |
| C | A,B | 10 |
| D | B | 5 |
| E | C,D | 7 |
| F | C, A | 5 |
| G | D | 4 |
| H | F,E,G | 6 |