Question: Q)John Doe the project manager is conducting a brainstorming session with the customer and reviewing the probabilities of certain risks which may occur over the
Q)John Doe the project manager is conducting a brainstorming session with the customer and reviewing the probabilities of certain risks which may occur over the life cycle of the project. The customer after reviewing them is classifying them as Low, Medium, and High. Which of the following type of an activity is being performed in this scenario?
a)Qualitative Risk Assessment
b)Quantitative Risk Assessment
c)Risk Ranking
d)Nominal Group Technique