Question: Q.No.3. (12 Marks) Develop a resource histogram for an IT project over six-months time frame by using the following table. Resources Jan Feb Mar Apr

Q.No.3. (12 Marks) Develop a resource histogram for an IT project over six-months time frame by using the following table. Resources Jan Feb Mar Apr May Jun Program Manager 1 1 1 1 1 1 Business Analysts 2 2 2 1 1 1 Programmers 1 1 4 4 4 1 Technical Writers 0 3 1 1 1 0