Question: Q-perform the resource leveling including the backward and forward pass for the initial project schedule shown in the following table, were numbers listed under an
Q-perform the resource leveling including the backward and forward pass for the initial project schedule shown in the following table, were numbers listed under an activity indicate it resource requirements per day.
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Activity Resources |
| C 3 | C 3 |
|
|
|
|
|
|
|
| Activity Resource | A 6 | B 7 | B 7 | E 2 | E 2 | G 6 | G 6 | H 3 | H 3 | I 6 |
| Activity Resource |
|
|
| D 2 |
| F 5 | F 5 |
|
|
|
| ACIVITY | A | B | C | D | E | F | G | H | I |
| SUCCESSOR | B,C | E,D | G | G | F,G | I | H | I |
|
IF(F,1) = R x [RV - RO (R X M)
IF(F,1) =
IF(F,2) =
IF(C,2)=
IF(D,1)=
Complete the backwards pass to identify the start time of the following
Activity F starts on day =
Activity D starts on day =
Activity C starts on day =
Activity G starts on day =
Calculate the resource leveling calculation by performing the forward pass
Activity D starts on day =
Activity F starts on day =