Question: QS 18-3 Cost behavior estimation-high-low method LO P1 The following information is available for a companys maintenance cost over the last seven months. Month Maintenance

QS 18-3 Cost behavior estimation-high-low method LO P1

The following information is available for a companys maintenance cost over the last seven months.

Month Maintenance Hours Maintenance Cost
June 11 $ 5,250
July 17 6,700
August 13 4,900
September 16 5,800
October 22 6,700
November 25 7,180
December 7 3,400

Using the high-low method, estimate both the fixed and variable components of its maintenance cost.

High-Low method - Calculation of variable cost per unit
Total cost at the high point
Variable costs at the high point:
Volume at the high point:
Variable cost per unit
Total variable costs at the high point
Total fixed costs
Total cost at the low point
Variable costs at the low point:
Volume at the low point:
Variable cost per unit
Total variable costs at the low point
Total fixed costs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!