Question: QSO 3 4 0 Project Two Guidelines and Rubric Competency In this project, you will demonstrate your mastery of the following competency: Determine appropriate methods
QSO Project Two Guidelines and Rubric
Competency
In this project, you will demonstrate your mastery of the following competency:
Determine appropriate methods to monitor and communicate the status of a project
Scenario
You are in the th week of the XYZ Business Workflow project, and things havent quite gone according to plan. At the end of the requirements analysis phase, your team told you the following information:
Feature F development is more complex than initially thought. It will take at least workweeks to complete.
Feature Customization C will take close to five workweeks.
The complete system testing will take a minimum of one and a half weeks due to the complexity of the systems involved.
You made some necessary resource and schedule adjustments in your plan and obtained stakeholder approval for the same.
However, due to delays in getting client approvals, UI design and development took one week more than estimated, which has now pushed all dependent tasks out by a week. Moreover, a resource availability issue has added three days to the Feature development effort.
You are scheduled to present a project status report at the end of the week at a stakeholders meeting that will include the clients representatives.
Directions
Project Status Report
Create a presentation for stakeholders describing relevant aspects of the current project status. Your presentation must include the following information:
Original and current project schedule
Current project status
Updated risk register
Any other relevant project information you believe the stakeholders need to know
You can use any project management software PMS tool to create and update the project schedule and status. However, remember to choose a tool that will help you complete all parts of the project, like the Gantt chart.
Specifically, your presentation must include the following rubric criteria:
General project information
List the project goal and objectives.
Include the team information.
Detail the initial schedule with milestones and end dates.
Current project status
Include a Gantt chart that shows the projects progress and current schedule.
Update the risk register. If an issue has occurred, add the issue to the Issue Log. An updated risk register includes the following information:
Status of risks from the project planning phase, including whether and how they have affected the project plan and schedule so far
Any issues facing the team currently and how you are managing them
Any new potential risks and proposed mitigation
Project summary
Include the updated milestone and end dates.
List action items to ensure the project stays on track.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock