Question: Quality Assurance engineer has made significant efforts to reduce its production variance from a = 0.042 to 0.035 using the same specifications of 6.40 +0.15.

Quality Assurance engineer has made significant
Quality Assurance engineer has made significant efforts to reduce its production variance from a = 0.042 to 0.035 using the same specifications of 6.40 +0.15. What is the Process Potential Index(C) value before the improvement when the process center was 6.35? O 1.1.190 O 2. 1.120 3.1.130 04.1.230