Question: Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects'
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 12%.
| 0 | 1 | 2 | 3 | 4 | ||||||
| Project A | -1,110 | 790 | 350 | 250 | 300 | |||||
| Project B | -1,110 | 390 | 285 | 400 | 750 | |||||
What is Project As IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
If the projects were independent, which project(s) would be accepted according to the IRR method?
-Select-NeitherProject AProject BBoth projects A and BCorrect 1 of Item 3
If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?
-Select-Neither Project AProject BBoth projects A and BCorrect 2 of Item 3
Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?
-Select-YesNoCorrect 3 of Item 3
The reason is -Select-the NPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same project acceptance when mutually exclusive projects are considered.the NPV and IRR approaches use different reinvestment rate assumptions and so there can be a conflict in project acceptance when mutually exclusive projects are considered.Correct 4 of Item 3
2)Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.
| 0 | 1 | 2 | 3 | 4 | ||||||
| Project A | -1,000 | 660 | 320 | 200 | 250 | |||||
| Project B | -1,000 | 260 | 255 | 350 | 700 | |||||
What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
$
What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
$
If the projects were independent, which project(s) would be accepted?
-Select-NeitherProject AProject BBoth projects A and BCorrect 1 of Item 3
If the projects were mutually exclusive, which project(s) would be accepted?
-Select-Neither Project AProject BBoth projects A and BCorrect 2 of Item 3
3)Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%.
| 0 | 1 | 2 | 3 | 4 | ||||||
| Project A | -900 | 500 | 320 | 380 | 310 | |||||
| Project B | -900 | 430 | 315 | 395 | 400 | |||||
What is Project Delta's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
What is the significance of this IRR?
It is the -Select-equity returncrossover rateinterest yieldCorrect 1 of Item 2, after this point when mutually exclusive projects are considered there is no conflict in project acceptance between the NPV and IRR approaches.
Review the graphs below. Select the graph that correctly represents the correct NPV profile for Projects A and B by using the following drop down menu.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
