Question: Quantity: 1 2 0 0 lb Production rate: 0 . 2 0 MH / lb Number of crews: 4 Productivity factor: 7 5 % productivity

Quantity:
1
2
0
0
lb
Production rate:
0
.
2
0
MH
/
lb
Number of crews:
4
Productivity factor:
7
5
%
productivity
(
operate at
7
5
%
capacity
)
Using this information, what is the estimated duration
(