Question: Queen Manufacturing uses 1 , 5 0 0 switch assemblies per week and then reorders another 1 , 5 0 0 . Assume the relevant
Queen Manufacturing uses switch assemblies per week and then reorders another Assume the relevant carrying cost per switch assembly is $ and the fixed order cost is $
Calculate the carrying costs.
Note: Do not round intermediate calculations and round your answer to the nearest whole number, eg
Calculate the restocking costs.
Note: Do not round intermediate calculations and round your answer to the nearest whole number, eg
Calculate the economic order quantity.
Note: Do not round intermediate calculations and round your answer to decimal places, eg
Calculate the EOQ number of orders per year.
Note: Do not round intermediate calculations and round your answer to decimal places, eg
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock