Question: Ques 3: Management has told you to get the project completed two weeks early. What is the best thing for you to do? A. Consult

 Ques 3: Management has told you to get the project completed

Ques 3: Management has told you to get the project completed two weeks early. What is the best thing for you to do? A. Consult the project sponso B. Crash C. Fast Track D. Advise management of the impact of the change