Question: Ques 3: Management has told you to get the project completed two weeks early. What is the best thing for you to do? A. Consult
Ques 3: Management has told you to get the project completed two weeks early. What is the best thing for you to do? A. Consult the project sponso B. Crash C. Fast Track D. Advise management of the impact of the change
Step by Step Solution
There are 3 Steps involved in it