Question: Question 1 0 0 . 5 pts Using a discount rate of 1 2 % , you calculate that your firm s new project has

Question 100.5 pts
Using a discount rate of 12%, you calculate that your firms new project has a Net Present Value of $0. This implies that...
Group of answer choices
a. The project has an (annualized) expected return of 0%.
b. Investing in the project would reduce the value of the firm.
c. The expected future cash flows from this project are $0.
d. The project has an (annualized) expected return of 12%.
e. The project is riskier than projects usually invested in by this firm.