Question: Question 1 0 ( 1 point ) A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective
Question point
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:
tableActivityDesignation,tableImmediatePredecessortableTime inDaystableBreak down bothmachinesANone,Clean machine BAClean machine CAtableReset machineDBtableReset machineECtableRecalibrate bothmachinesFD and EFinal test,,F
Using CPM which activities make up the critical path?
A D E