Question: Question 1 0 ( 1 point ) The key to effective project control is A ) assigning a specific resource to gather data from the
Question point
The key to effective project control is
A assigning a specific resource to gather data from the project team.
B measuring actual progress and comparing it to planned progress.
C calculating the costs of the project.
D communicating with the project sponsor and the stakeholders for the project.