Question: Question 1 0 . 2 5 0 . 2 5 pts A factory consists of three work centers: A , B and C . All

Question 1
0.250.25 pts
A factory consists of three work centers: A, B and C. All material must go through these three work centers in sequence (A, then B, then C).
The capacities of the work centers are:
A: 800 per day
B: 700 per day
C: 650 per day.
The bottleneck in this system is
Correct!
work center A
Good job. A is the bottleneck.