Question: Question 1 . ( 0 . 5 point ) Draw an activity on arrow network diagram for the following project. table [ [ Activity
Question point
Draw an activity on arrow network diagram for the following project.
tableActivityDuration DaysPredecessorsA Excavate,NoneB Build Forms,NoneC Procure Reinforcing Steel,NoneD Fine Grade,AE Set Forms,A and BF Place Reinforcing Steel,C D and EG Place and Finish Concrete,F