Question: Question 1 0 As the Project Manager, for a project that started 3 months ago, you review the project budget and notice a deviation due

Question 10
As the Project Manager, for a project that started 3 months ago, you review the project
budget and notice a deviation due to the increased resource hours of weekend overtime
work over to meet aggressive project deadlines. You call a meeting to identify how to
bring the project back into compliance. What common monitoring and controlling activity
is this an example of?
Controlling
Monitoring
Auditing
Evaluating