Question: Question 1 0 Calculating the for each activity in a CPM analysis helps to better prepare for and handle unforeseen circumstances on noncritical activities without
Question
Calculating the for each activity in a CPM analysis helps to better prepare for and handle unforeseen circumstances on noncritical activities without disrupting critical path activities.
expected time to completion
downtime
productivity
early start schedule
annual profitability